Lonesome
Pine Regional Business & Technology Park

DESCRIPTION
OF TABLES – Table 9
Preliminary
Statement of Probable Project Cost for the Lonesome Pine
Regional Business & Technology Park Stormwater Management
|
Construction |
Cost: |
|
|
Stormwater detention pond, L.S. |
$ 300,000 |
|
2,600 L.F. storm drains @ $60/L.F. |
156,000 |
Subtotal |
$ 456,000 |
|
Contingency (10% of Construction Cost) |
$ 46,000 |
TOTAL CONSTRUCTION COST |
$ 502,000 |
Related |
Cost: |
|
20% of Total Construction Cost |
$ 101,000 |
TOTAL RELATED COST |
$ 101,000 |
TOTAL PROJECT COST |
$ 603,000 |
|