Preliminary Statement of Probable Project Cost for the Lonesome
Pine Regional Business & Technology Park East Loop Road
|
Construction |
Cost: |
|
|
177,600 S.F. site preparation @ $1.75/S.F. |
$ 310,800 |
|
80,800 S.F. pavement @ $1.75/S.F. |
141,400 |
|
6,800 L.F. curb & gutter @ $15/L.F. |
102,000 |
|
12,000 S.F. sidewalks @ $2/L.F. |
24,000 |
|
10,600 C.Y. earthwork @ $5/C.Y. |
53,000 |
|
3,700 L.F. storm drains @ $60/L.F. |
222,000 |
|
14 EA. curb inlets @ $5,000/EA. |
70,000 |
|
5 Acres seeding @ $1,500/Acre |
7,500 |
|
Erosion and sediment control, L.S. |
40,000 |
Subtotal |
$ 970,700 |
|
Contingency (10% of Construction Cost) |
$ 98,000 |
TOTAL CONSTRUCTION COST |
$ 1,068,700 |
Related |
Cost: |
|
20% of Total Construction Cost |
$ 214,000 |
TOTAL RELATED COST |
$ 214,000 |
TOTAL PROJECT COST |
$ 1,282,700 |
|