Lonesome
Pine Regional Business & Technology Park

DESCRIPTION
OF TABLES – Table 7
Preliminary Statement of Probable Project Cost for the Lonesome
Pine Regional Business & Technology Park West Loop Road
|
Construction |
Cost: |
|
|
138,400 S.F. site preparation @ $1.75/S.F. |
242,200 |
|
62,800 S.F. pavement @ $1.75/S.F. |
109,900 |
|
5,300 L.F. curb & gutter @ $15/L.F. |
79,500 |
|
9,300 S.F. sidewalks @ $2/L.F. |
18,600 |
|
47,800 C.Y. earthwork @ $5/C.Y. |
239,000 |
|
2,900 L.F. storm drains @ $60/L.F. |
174,000 |
|
11 EA. curb inlets @ $5,000/EA. |
55,000 |
|
23 Acres seeding @ $1,500/Acre |
34,500 |
|
Erosion and sediment control, L.S. |
31,000 |
Subtotal |
$ 983,700 |
|
Contingency (10% of Construction Cost) |
$ 99,000 |
TOTAL CONSTRUCTION COST |
$ 1,082,700 |
Related |
Cost: |
|
20% of Total Construction Cost |
$ 217,000 |
TOTAL RELATED COST |
$ 217,000 |
TOTAL PROJECT COST |
$ 1,299,700 |
|