Preliminary
Statement of Probable Project Cost for the
Lonesome Pine Regional Business & Technology Park
State Route 723 Road Improvements |
Construction |
Cost: |
|
|
62,500 S.F. demolition @ $0.30/S.F. |
$ 18,800 |
|
128,000 S.F. site preparation @ $1.75/S.F. |
224,000 |
|
58,400 S.F. pavement @ $1.75/S.F. |
102,200 |
|
4,900 L.F. curb & gutter @ $15/L.F. |
73,500 |
|
8,700 S.F. sidewalks @ $2/L.F. |
17,400 |
|
7,600 C.Y. earthwork @ $5/C.Y. |
38,000 |
|
2,600 L.F. storm drains @ $60/L.F. |
156,000 |
|
10 EA. curb inlets @ $5,000/EA. |
50,000 |
|
4 Acres seeding @ $1,500/Acre |
6,000 |
|
Erosion and sediment control, L.S. |
29,000 |
Subtotal |
$ 714,900 |
|
Contingency (10% of Construction Cost) |
$ 72,000 |
TOTAL CONSTRUCTION COST |
$ 786,900 |
Related |
Cost: |
|
20% of Total Construction Cost |
$ 158,000 |
|
TOTAL RELATED COST |
$ 158,000 |
|
TOTAL PROJECT COST |
$ 944,900 |
|