Lonesome
Pine Regional Business & Technology Park

DESCRIPTION
OF TABLES
Preliminary
Statement of Probable Project Cost For the
Lonesome Pine Regional Business & Technology Park
Bear Creek Sanitary Sewer Extension |
|
|
Construction |
Cost: |
| 14,200
L.F. 10-inch gravity sewer line @ $48/L.F. |
$
681,600 |
| 10,500
L.F. 8-inch gravity sewer line @ $42/L.F. |
441,000 |
| 1,250
L.F. 4-inch service lateral @ $18/L.F. |
22,500 |
| 92
EA. standard manholes @ $1,800/EA. |
165,600 |
| 8
EA. drop manholes @ $2,000/EA. |
16,000 |
| 150
V.F. manhole extensions @ $90/EA. |
13,500 |
| 25
EA. 4-inch service wyes @ $90/EA. |
2,250 |
| 25
EA. 4-inch plugs @ $15/EA. |
375 |
| 25
EA. 4-inch cleanouts @ $200/EA. |
5,000 |
| 2
EA. road crossings @10,000/EA. |
20,000 |
| 350
Tons miscellaneous aggregate @ $15/Ton |
5,250 |
| 175
C.Y. miscellaneous concrete @ $150/C.Y. |
26,250 |
Subtotal |
$1,399,325 |
| Construction
Contingency (10% of Total Construction Cost) |
$
140,000 |
TOTAL
CONSTRUCTION COST |
$1,539,300 |
Related |
Cost: |
| 20%
of Total Construction Cost |
$
308,000 |
TOTAL
RELATED COST |
$
308,000 |
TOTAL
PROJECT COST |
$1,847,300 |
|