| Lonesome
Pine Regional Business & Technology Park

PROJECT
COSTS
Project costs have
been developed for the infrastructure considered necessary to
accommodate access and development of each parcel of the Park.
These costs are presented in independent segments in order to
provide for maximum flexibility in the Park development. The infrastructure
necessary to accommodate the ultimate development of the Park
includes water system improvements, a sanitary sewer system, roads,
and stormwater management. Costs for buildings and individual
site development are not included in this report since these costs
are site and tenant specific. Also, telephone and electrical utility
costs are not included in these infrastructure estimates. This
report assumes that the costs of telephone and electrical utilities
will be prorated into the ultimate user fees. An Infrastructure
Site Schematic included in Appendix A of this report depicts the
complete infrastructure for which costs have been provided.
The project costs are
based upon preliminary layouts, descriptions, and service area
design calculations and, therefore, represent preliminary statements
of probable project costs for the Lonesome Pine Regional Business
& Technology Park Master Plan. Table 1 summarizes the project
costs for each independent segment of the Park infrastructure.
Tables 2 through 9 itemize more detailed probable costs for each
of the independent segments.
Project costs
are defined as the sum of estimated construction costs and related
costs. It should be noted that 10 percent of the estimated construction
cost has been assumed to cover contingency items. It is important
to stress that these costs are subject to further revision as
field surveys are completed and detailed plans are developed for
the project. Experience on similar projects, manufacturers’
cost information, and actual unit cost bids received on similar
projects were utilized during the calculation of all project costs
(i.e., construction and related costs).
|